Following Ontario Ministry of Environment water-taking guidelines, Caledon Country Club moved forward on a new inline irrigation reservoir. Gateman Milloy was responsible for all earthworks including strip and stockpiling of native topsoil, engineered balanced cut/fill and topsoil replacement. The scope of work also included the installation of a pre-cast intake structure within the bank of the Credit River along with associated HDPE piping to transfer water from creek into reservoir, approximately 500 meters. Two wet-well structures were required — one at the creek for the transfer pump to move water from the creek intake to the reservoir, and the second at the reservoir for the irrigation pump station.

Caledon Country Club, Inglewood, Ontario